As summer continues, neighbors are anticipating exercising on the Northaven Trail.

Phase 2a is still under construction, but segments 2b and 2c, which runs from Cinderella Lane to Denton Drive, open Saturday, June 29.  Join neighbors to celebrate the opening at a ribbon cutting ceremony Saturday at Joe’s Creek Bridge at 10 a.m.. If you use a trusty GPS or Google Maps, plug in 1131 Rosser Road. This is not the address for the trail, but rather a home address that is near the festivities.

Section 2a, from Preston to Cinderella, is still under construction. This section should be completed this fall, but it is currently still an active construction zone.

The trail has taken longer to complete than anticipated. In 2018, it was announced that phases 2b and 2c would be finished by the end of 2018, and that 2a would be completed in 2019. Phase 1 is already completed and open for use.

For a map of the trail, click here. To find out more about plans for the trail, visit Friends of Northaven Trail.